2023 Asphalt Pavement Preventive Maintenance Project

Because of weather delays, the fog seal work is completed for 2023.  All remaining roadways will be rescheduled for fog seal installation in the spring of 2024.  Once a schedule has been established it will be posted here.  Please also look for signs that will be installed the day before the work takes place.  The overband crack filling was completed in the fall of 2023.

Roadways that were resurfaced in 2023 have been added to this project and will be completed when the contractor re-mobilizes in the spring of 2024, as this will extend the life of the new pavement. These roadways are shown in the map below but are pending a change order.  

 

This project is being undertaken to install a fog seal and crack seal on approximately 9 miles asphalt roadways throughout the City.  During the closures house that front on selected roadways will not have access to their driveways.  Please plan to park on a nearby side street if the vehicle will be needed the day of the closure.  Overnight parking restrictions will be waived for the duration of the project. Please do not park on the street the night before a roadway is scheduled to be treated.  

An interactive map can be found HERE.  The map shows the roadways included in this project and the dates each roadway is scheduled to be closed & treated (fog sealed). A detailed schedule for the remaining roadways and any additions will be posted once it has been provided to the City by the contractor.

Highlights for those fronting the road closures:

  • Do not park on the street the night before a roadway is scheduled to be closed
    • on street parking restriction will be waived in the project areas for the project duration.
  • Do not run sprinklers the night before or morning of the scheduled treatment.
  • Closures will be 4-6 hours in duration
  • Work will be undertaken in the order shown on the map and schedule.
    • Please note if your roadway is listed later for a given day the closure may not be in place until the early afternoon.

If you have any further questions please direct them to Assistant City Engineer Alex Austin, telephone: (269) 983-5541, email: aaustin@sjcity.com