Category B & 2025 Resurfacing Projects
The City recently awarded both the Category B & 2025 Resurfacing Projects to Michigan Paving Materials Company (MPM). These projects are being undertaken to resurface several asphalt roadways throughout the City of St. Joseph by removing ~1.5-2" of the existing asphalt and replacing it with new asphalt. The resurfacing work will require short duration road and lane closures during the removal and the placement of the asphalt. During the closures, homes that front on selected roadways will not have access to their driveways. Please plan to park on a nearby side street if the vehicle will be needed the day of the closure. Overnight parking restrictions will be waived for the duration of the project. Please do not park on the street the night before a roadway is scheduled to be resurfaced.
Important Information for Residents Along the Project Area
- Work will be completed under lane closures with flaggers to maintain traffic flow. No full road closures are expected.
- Lane closures will only be in place while the contractor is completing the work and roadways will be fully open at the end of each day.
- Please use caution when driving on milled surfaces — they will be rougher, with approximately 2-inch drops at milling limits.
- Work can start as early as 7 AM.
- Do not park on the street the night before a roadway is scheduled for work.
- If you are concerned about being delayed leaving in the morning, please park on a nearby street not included in the project (where available).
- On street parking restrictions will be waived in project areas for the duration of the project.
- Do not run sprinklers the night before or morning of the scheduled paving.
Work Schedule (as of 10/17/2025)
Roadway | From | To | Structure Temp Lowering | Milling | Paving |
Golden Bear Ct | M-63 | Dead End | Completed 10/16 | Tuesday, October 21, 2025 | |
Anchors Way | Anchors Ct | Condo Entrance | Completed 10/16 | Tuesday, October 21, 2025 | |
Morton Ave | St. Joseph Dr | Highland Ave | Completed 10/17 | Thursday, October 23, 2025 | |
Pearl St | Court St | Wayne St | Completed 10/17 | Wednesday, October 22, 2025 | |
Olive St | Pearl St | Market St | Completed 10/17 | Wednesday, October 22, 2025 | |
Marsh St | Broad St | Marina Entrance | Completed 10/17 | Wednesday, October 22, 2025 | |
Pleasant St | Lake Blvd | Court St | Wednesday, October 22, 2025 | Friday, October 24, 2025 | |
Morton Ave | Botham Ave | Van Brunt Ave | Wednesday, October 22, 2025 | Friday, October 24, 2025 | |
Midway Ave | S State St | Niles Ave | 10/20/2025 | Wednesday, October 22, 2025 | Monday, October 27, 2025 |
St. Joseph Dr | S State St | Washington Ave | 10/20/2025 | Wednesday, October 22, 2025 | Monday, October 27, 2025 |
While both projects are similar in scope the funding sources differ. The 2025 Resurfacing Project is funded by city funds entirely while the Category B Resurfacing Project is receiving a 50% grant from the State of Michigan.
A map for the 2025 Resurfacing Project can be found HERE.
A map for the Category B Resurfacing Project can be found HERE.
If you have any further questions please direct them to Assistant City Engineer Alex Austin, telephone: (269) 983-5541, email: aaustin@sjcity.com