2025 Botham Avenue Reconstruction Project

Botham Overview

July 21, 2025 Project Update

Hoffman Brothers, the Contractor on the Botham Avenue Reconstruction Project has informed ROWE Professional Services Company and City Staff that construction is now scheduled to begin August 7th, 2025.  The project is expected to be finished mid-October to meet the progress clause; work on Saturdays may be necessary to meet that date.

The power point from the public meeting held on July 9, 2025 is posted below.

Thank you for your understanding and please feel free to contact Mike Roberts, at (616) 481-4512 or Assistant City Manager/City Engineer, Tim Zebell at (269) 985-0339 with questions or concerns.